Date:
Sat, 10 Sep 2005 18:46:30 -0400
From:
David Cheifetz
Subject:
Law of Contract and unconscionability
Jason,
I
apologize in advance for the length of this reply.
Gottardo
is another example of an appellate court not being careful enough
in both what it does say and it what it doesn't, about issues it
thinks it doesn't have to deal with.
Gottardo
makes it necessary to ask (in Ontario) ask: when the court is asked
to enforce (relieve against) the performance of a contract, when
will it be unconscionable, unfair or unreasonable to irreparably
damage/destroy a business as the result of the enforcement or relief
from enforcement? Or, more to the point when is it not?
TTC
v Gottardo may or may not be problematic for tender law. It
opens a can of worms (in Ontario, at least) on the broader question
of the scope of the power to decline to enforce otherwise valid
contracts or terms of a contract on the basis of unconscionability
because it makes a broad statement about the power without any indication
of the parameters of the statement.
Gottardo
should also be understood as another example of a case where, for
some reason, an appellate court didn't accept consequences necessarily
flowing from underlying facts as found by the trial judge but it
couldn't validly alter the findings of fact. So it chose to ignore
the uncomfortable facts.
If
you take the case literally, it means that a financial mistake which,
on the evidence "cause severe and irreparable financial hardship"
is not sufficient to trigger the courts power to decline to enforce
contracts (or contractual terms) for "unconscionability": that it's
not unconscionable to do so or not unfair or unreasonable to do
so. I use the alternatives because we still don't have an SCC answer
as to which formulation is the description of the power - although
those of us in Ontario have been told by the CA (accepting Waddam's
view) that in practice there's not likely to be a significant difference.
The SCC's most recent statement (as sparse as it is) is still Hunter
Engineering v Syncrude [1989] 1 SCR 425 and as good a discussion
as any of the case, for those who don't know it (or remember it)
is Robert Flannigan's "Hunter Engineering: The Judicial
Regulation Of Exculpatory Clauses" [1990] 69 Canadian Bar Review
514.
The
facts of Gottardo are simple. There was an addition mistake
of $557,000 on the Gottardo bid at $4.81 .million. It should have
been $5,368,492.40. The TTC was advised of the mistake after the
tenders were opened but before it accepted the Gottardo bid. Nonetheless,
the TTC accepted the bid. Gottardo, of course, refused to perform
so the TTC awarded the contract to the next lowest bid - about $434,000
higher - then claimed on the Gottardo bid bond put up by G's insurer,
CGU. So, there was no change of position, reliance, etc. by the
TTC. And, one more telling fact: undisputed, uncontradicted evidence
that "if the TTC took action against the bid bond, it would cause
severe and irreparable financial hardship to Gottardo.
[The
TTC initially claimed the entire bond - 532K, not just the 434,000
difference - but no doubt that was for good motives: no doubt, it
had in mind the interest of Toronto's citizens.]
The
trial judge held that if Contract A came into existence Gottardo
was entitled to rescind. Here are the operative paragraphs from
the trial reasons:
69
I have found that Gottardo made an honest and inadvertent mistake
that was communicated to the TTC after the deadline for submitting
tenders but on the same day and before the TTC had accepted the
bid or had changed its position in reliance on the bid. The mistake
is as to a fundamental term of Contract A, namely it represents
the price of performing seven enumerated items in the price schedule.
On that basis, the court is entitled to entertain the request for
rescission.
71
In my view it would be unfair and unjust to enforce Contract A for
these reasons:
(a)
This case is not fundamentally about the integrity of the public
bidding process. Rather, it is fundamentally about the interpretation
of the Instructions to Tenderers the drafting of which was wholly
in the control of the TTC.
(b)
I have found that Gottardo made an honest and inadvertent mistake.
It is not a situation, as suggested by Lee, of a contractor saying:
oh guess what, I don't want this for whatever reason. Gottardo had
a logical explanation.
(c)
From December 20th when Gottardo's letter was received by the TTC,
officials rejected his request out of hand. There is no evidence
that any consideration was given by TTC that perhaps its own contractual
language distinguished it from the legal position on which it relied.
Instead, on the recommendation of its staff, TTC "snapped at it";
(d)
The evidence of Gottardo is consistent with what he said in his
December 20th letter, namely that if the TTC took action against
the bid bond, it would "cause severe and irreparable financial hardship".
Mr. Gillott took the position that that evidence ought not to be
accepted without corroboration. However, there was no cross-examination
on that part of Gottardo's evidence. There is no reason not to accept
it and I do;
(e)
The "commercial advantage" argument appears to be based on the decision
of the trial judge in Ron Engineering where he described the "brinkmanship
with the sub-trades", a practice "obviously" for the benefit of
the tenderer. The Supreme Court of Canada did not comment on that
argument. I agree that the tenderer reaps some advantage from the
"brinkmanship with the sub-trades". But it is ultimately the owner
who benefits from the highly competitive bidding which is generated
in the typical public tender process, the rules for which are established
by the owner. The fact that Gottardo may have achieved some "commercial
advantage" over its competitors does not mean that it is disentitled
to equitable relief;
(f)
there was no fraud or misrepresentation or other act on the part
of the TTC which induced or contributed to the mistake on the part
of Gottardo. But as pointed out above, the threshold is not the
conduct of the offeree. The threshold is the effect on the offeror.
72
In this alternative scenario, if Contract A was created, the TTC
is not entitled to enforce it. Gottardo is entitled to rescission.
While
there was no evidence as to what the financial hardship might have
been, we can make an astute guess. Gottardo Co. and its principals
jointly guaranteed the bid bond so that the 434,000 that CGU had
to pay would ultimately come out of the Gottardo/principals' pocket(s).
Here's
how the Ont CA dealt with the rescission defence. The italics of
the 3rd and 2nd last sentence are mine.
[32]
The trial judge's reasons make it clear that the mistake was unilateral
and that there was no fraud. The trial judge, however, found that
since the mistake was honestly made and inadvertent and because
enforcement would cause Gottardo financial hardship, she would
grant rescission. With respect, I do not agree. In my view, there
are no unique circumstances in this case which distinguish it
from Ron Engineering and which would operate so as to
entitle the tenderer to have the contract rescinded. While it
is conceded that some financial hardship will flow from enforcement
of the contract, this is not sufficient to warrant rescission.
The burden imposed on Gottardo by the enforcement of the contract
freely entered into is not so grossly disproportionate so as to
make enforcement of it by the courts unconscionable. In the circumstances,
there are simply no grounds for equitable intervention.
Anybody
care to speculate what "grossly disproportionate" means? Disproportionate
to what? How much financial burden would have been sufficient? The
practical destruction of Gottardo or its principals? The only "burden"
that would be imposed on Gottardo would be a financial burden, so
the 3rd last sentence can't mean that financial consequences are
never enough of themselves; only that they weren't enough here.
The undisputed evidence (last I checked the law, the CA isn't supposed
to reverse unchallenged findings of fact that could be correct just
because it doesn't like the "smell" of the finding) was that Gottardo
would suffer "severe and irreparable financial hardship" - look
at para 71(d) of the trial judgment quoted above. On what basis
does the CA call that only "some financial hardship?" Or did the
CA consider the trial finding hyperbole? Why wasn't that sufficient
to trigger the remedy of recession under the CA's formulation in
para 72, unless the CA meant to say that even irreparable financial
hardship isn't enough. But that isn't what the paragraph says.
How
much financial hardship would have been enough to trigger unconscionability?
Bear in mind there was a bid bond which applied - the judgment was
jointly against Gottardo and the insurer CGU - so the only reason
Gottardo might have had any financial hardship is if it or its principals
guaranteed the bond so had to repay the insurer. And the consequences
of CGU calling on the guarantee, as it no doubt would.
Anybody
care to speculate what law the CA panel looked to for the decision
that enforcement of Contract A wouldn't be unconscionable? It couldn't
have been Ron Engineering at the SCC, because that issue
wasn't discussed.
The
CA could well wrong in the blanket assertion that "there are no
unique circumstances in this case which distinguish it from Ron
Engineering and which would operate so as to entitle the tenderer
to have the contract rescinded" so long as we're prepared to concede
that SCC decisions after Ron Engineering could be relevant.
I'm not certain what the CA meant by "unique circumstances" but
I'd hazard a change in the law is relevant, even if not "unique".
Ron Engineering was decided in 1981. The SCC's last word,
in the contract context, on the scope of the "unconscionability"
doctrine is 1989's Hunter Engineer v Syncrude. Hunter
isn't discussed in Gottardo at either level. Ultimately,
the unconscionability principle (whatever it comes to mean) will
control the recission remedy. The CA even used the telling phrase
"so as to make enforcement of it [the contract] unconscionable".
The
amount of the error in Ron Engineering was about $750,000
on a $2.75M bid which should have been about $3.5 if the addition
was right so the mistake was about 21% of the contractor's correct
estimate. Gottardo's error was "only" a bit more than 10% of its
estimate - $557,000 on about $5.38M. So, if we assume that the SCC
said in Ron Engineering that a 20% difference was not sufficiently
disproportionate, of itself, to render enforcement unconscionable
so as to permit rescission, then the CA was right in stating " there
are no unique circumstances in this case which distinguish it from
Ron Engineering" etc.
There
are at least two problems with that conclusion. The first is that
the on Ron Engineering doesn't have any discussion of the
rescission remedy or unconscionability and it predates Hunter
Engineering. So the CA couldn't have found its "unconscionability"
law in Ron Engineering and that new law could require a
change in the result. The second is that there's nothing in the
SCC decision that mentions financial hardship to Ron Engineering,
probably because the deposit forfeited was "only" $150,000.
Now
those of us who practice in Ontario have try to guess what the Ont
CA thinks about the scope of the unconscionability power as a ground
for declining to enforce an otherwise valid contract or term in
a contract. Does this mean that, the next time the Ont CA has to
consider the SCC's decision in Hunter Engineering we have
TTC v Gottardo as a hint that in Ontario it's Wilson J.
's unfair, unreasonable in application rather than Dickson's J's
unconscionability? Since it's really only Wilson J's version that
looks to the time of the contract's performance, rather than it's
making, for the relevant criteria. Or was it Dickson J's test with
the CA saying that it was prepared to assume that contract B - the
construction contract - could not have been performed except at
some amount of meaningful (though not necessarily sufficient) financial
hardship. I appreciate that Waddams says they're practicably the
same (and the Ont CA has approved this comment). I beg to differ.
Regards,
David
-----------------
David
Cheifetz
Bennett Best Burn LLP
Toronto, Canada
-----
Original Message -----
From: Jason Neyers
Sent: Saturday, September 10, 2005 8:31 AM
Subject: ODG: The Law of Tenders
Dear
Colleagues:
Those
of you interested in the Canadian law of tenders, will be interested
in the Ont. CA's decision in Toronto
Transit Commission v. Gottardo Construction Limited which
deals with contract A and the effect of mistake and rescission.
<<<<
Previous Message ~ Index ~ Next
Message >>>>>
|