Date:
Tue, 13 Sep 2005 10:19:28 -0400
From:
David Cheifetz
Subject:
Mistakes in Tendering
John,
Fast
and loose with the law, too, since none of rescission or any other
(equitable or legal) remedy / basis for relieving Ron Engineering
from compliance with a valid contract A were argued. The SCC even
said, specifically, that it wasn't dealing with penalty / relief
from forfeiture issues because they hadn't been raised. So, the
only issue in Ron was whether contract A came into existence.
To imply otherwise, as the CA did in para 32 of Gottardo
is unfortunate, to say the least.
I
disagree with David’s suggestion that some solution might lie
in unconscionability: the problem is not that there is any unfairness
in the transaction. The unfairness comes, as I have said, from
the courts’ refusal to deal sensibly with a problem that really
isn’t very hard to solve.
My
unconscionability reference went to the issue of relieving from
the consequences of enforcing valid contract A, not the issue of
whether contract A came into existence. My apologies as it seems
I didn't make that clear. The posting was rushed.
On
the enforceability issue:
If
the finding is that contract A came into force, but the issue is
whether the owner will be allowed to enforce contract A, - to keep
the deposit, to collect on the bid bond, to sue for the difference
between the contract price under the lower bid and the higher price
ultimately paid - and that's a valid question, then aren't we asking
ourselves under what circumstances the courts will relieve against
the performance of an otherwise valid contract? If that's so, if
there's a unifying principle to all of the remedies, doesn't it
now lie in some concept of unconscionability?
Going
back to Gottardo, assume there'd been a cash deposit (rather
than a bid bond) which the TTC had been holding and it refused to
return. (It shouldn't make a difference, of course, that it was
a bid bond that the TTC claimed on, since there was finding that
payment was due under the bond.) Assume Gottardo had sued the TTC
arguing that the TTC would be unjustly enriched if it was permitted
to keep the deposit. We have enrichment and corresponding deprivation.
Is there a juristic reason for allowing the TTC to keep the money?
If there is, what would it be? Saving money for the over-burdened
TTC? As you said, it isn't clear what motivated the CA.
And,
if we can make the argument that way, isn't another indication that
unconscionability, whatever it means, is lurking somewhere in the
background?
Regards,
David
Cheifetz
-----
Original Message -----
From: John Swan
Sent: Tuesday, September 13, 2005 9:15 AM
Subject: ODG: Mistakes in Tendering I
can understand and agree with David's anger at the Court of Appeal’s
decision in Gottardo. First,
this is (at least) the second time this year in which the Court
of Appeal has played fast and loose with a trial judge's findings
of fact and done a bad job of justifying it. The other case is
Amertek Inc. v. Canadian Commercial Corp. It is not
clear to me what motivated the Court in each case. Second,
in dealing with the issues of Ron Engineering — one of
the most dreadful decisions of the Supreme Court — it is important
to notice what both the CCDC and the rules of the various Bid
Depositaries provide. They provide that a contractor or subcontractor
who makes a mistake can withdraw its bid but may not submit another.
This solution is both fair and reasonable. The owner or general
contractor cannot claim to have relied on the mistaken bid (except
when the subcontractor’s bid is incorporated into the general
contractor’s tender; see Northern Construction Co. Ltd. v.
Gloge Heating & Plumbing Ltd. (1985), 27 D.L.R. (4th) 264,
[1986] 2 W.W.R. 649) and denying relief for the tenderer‘s mistake
simply gives the owner a windfall. It’s the pointlessness of that
windfall in Ron Engineering, Gottardo and many
other cases that is so upsetting. This fact was recognized by
Kerans J.A. in Calgary v. Northern Construction Co. Division
of Morrison- Knudsen Company Inc., [1986] 2 W.W.R. 426, 42
Alta. L.R. (2d) 1, 67 A.R. 95, 32 B.L.R. 81, aff'd, [1987] 2 S.C.R.
757, [1988] 2 W.W.R. 193, 56 Alta. L.R. (2d) 193. When
Estey J. in Ron Engineering was talking about maintaining
the "integrity of the bidding process", he was doing
all that he could to subvert it and to provide an incentive for
an owner to seek to profit from a mistake made by a contractor
when the owner had suffered no loss. A
large part of the tragedy of Ron Engineering is the fact
that until the Supreme Court got its hands on the question, the
courts of appeal, particularly the Ontario Court of Appeal, had
been doing a very good job in working out fairly and sensibly
how to deal with mistakes in tendering. The construction industry
was aghast at the decision in Ron Engineering and could
hardly believe that the Supreme Court could have been so unaware
of what the industry did.
The
result is, of course, that we have all the problems that one would
expect from a dreadful decision, constant efforts of trial judges
to reach fair results and no serious or coherent efforts from
courts of appeal to undo the damage. By
the way, does anyone know what Iacobucci J. had in mind when he
said that he wasn’t sure about the Contract A analysis of Ron
Engineering in M.J.B. Enterprises? The problem with
the result in Ron Engineering and Gottardo has
nothing to do with the Contract A analysis, but everything with
the courts’ blindness to sensible solutions to a common problem
when there are readily available satisfactory models to choose
from. I
disagree with David’s suggestion that some solution might lie
in unconscionability: the problem is not that there is any unfairness
in the transaction. The unfairness comes, as I have said, from
the courts’ refusal to deal sensibly with a problem that really
isn’t very hard to solve.
<<<<
Previous Message ~ Index ~ Next
Message >>>>>
|