![]() |
RDG
online Restitution Discussion Group Archives |
||||||||||||
![]() |
![]() |
||||||||||||
|
Dear all,
The US SCt yesterday handed down an interesting and important
decision ordering the Federal Government to make restitution of US$158m
paid by two oil companies under contracts of exploration repudiated by
the Government.
I think that, outside the US, the question would have
been whether the termination for breach amounted to a total failure of
consideration. However, US law seems not to have inherited the failure
of consideration cause of action in those terms, and certainly not to
have inherited the total failure bar. Most of the case is concerned with
whether the Government's actions amounted to a breach sufficiently serious
to terminate the contract (yes), and with whether the plaintiffs could
be said subsequently to have affirmed the contract (no); restitution consequent
upon a finding of repudiatory breach seems to have been regarded almost
as self-evident.
Eoin O'Dell.
=========================================
MOBIL OIL EXPLORATION & PRODUCING SOUTHEAST, INC. v.
UNITED STATES (99-244)
Web-accessible at: http://supct.law.cornell.edu/supct/html/
99-244.ZS.html
Argued March 22, 2000 -- Decided June 26, 2000
Opinion author: Breyer
Together with No. 99-253, Marathon Oil Co. v. United
States, also on certiorari to the same court.
=========================================
Two oil companies, petitioners here, paid the Government
$158 million in return for lease contracts giving them the rights to explore
for and develop oil off the North Carolina coast, provided that the companies
received exploration and development permission in accordance with procedures
set out in, inter alia, the Outer Continental Shelf Lands Act (OCSLA),
the Coastal Zone Management Act of 1972 (CZMA), and regulations promulgated
pursuant to those Acts. OCSLA, among other things, requires the Department
of the Interior to approve a company's Plan of Exploration (Plan) within
30 days of its submission if the Plan meets certain criteria. A company
must also obtain an exploratory well drilling permit after certifying
under CZMA that its Plan is consistent with each affected State's coastal
zone management program. If a State objects, the Secretary of Commerce
must override the objection or the certification fails. Interior may grant
the permit if Commerce rules against the State. While the companies' Plan
was pending before Interior, the Outer Banks Protection Act (OBPA) became
law. OBPA prohibited the Interior Secretary from approving any Plan until,
inter alia, an OBPA-created Environmental Sciences Review Panel (Panel)
reported to the Secretary and the Secretary certified to Congress that
he had sufficient information to make OCSLA-required approval decisions.
In no event could he approve any Plan for 13 months. Interior told Mobil
the Plan met OCSLA requirements but that it would not approve the Plan
until the OBPA requirements were met. It also suspended all North Carolina
offshore leases. After the Panel made its report, the Interior Secretary
made the requisite certification to Congress but stated that he would
not consider the Plan until he received further studies recommended by
the Panel. North Carolina objected to the CZMA certification, and the
Commerce Secretary rejected Mobil's override request. Before the Commerce
Secretary issued his rejection, the companies joined a breach of contract
lawsuit in the Court of Federal Claims. That court granted them summary
judgment, finding that the Government had broken its contractual promise
to follow OCSLA, that the Government thereby repudiated the contracts,
and that that repudiation entitled the companies to restitution of their
payments. In reversing, the Federal Circuit held that the Government's
refusal to consider Mobil's Plan was not the operative cause of any failure
to carry out the contracts' terms because the State's objection to the
CZMA certification would have prevented the exploration.
Held: The Government broke its promise, repudiated the
contracts, and must give the companies their money back. Pp. 8-19.
(a) A contracting party is entitled to restitution if
the other party "substantially" breached a contract or communicated its
intent to do so. Here, the Government breached the contracts and communicated
such intent. None of the provisions incorporated into the contracts granted
Interior the legal authority to refuse to approve the companies' Plan,
while suspending the lease instead. First, such authority does not arise
from the OSCLA provision, 43 U.S.C. sect. 1334(a)(1)(A), that permits
the Secretary to promulgate regulations providing for suspension of an
operation or activity only upon "the request of a lessee." Second, the
contracts say that they are subject to then-existing regulations and future
regulations issued under OCSLA and certain Department of Energy Organization
Act provisions. This explicit reference to future regulations makes it
clear that the contracts' catchall provisions referencing "all other applicable
... regulations" must include only statutes and regulations already existing
at the time of the contracts. Thus, the contracts are not subject to future
regulations promulgated under other statutes, such as OBPA. Third, an
OSCLA provision authorizing suspensions in light of a threat of serious
harm to the human environment did not authorize the delay, for Interior
explained that the Plan fully complied with current legal requirements
and cited OBPA to explain the delay. Insofar as the Government means to
suggest that OBPA changed the relevant OSCLA standard, it must mean that
OBPA in effect created a new requirement. Such a requirement would not
be incorporated into the contracts. Finally, when imposing the delay,
Interior did not rely upon any of the regulations to which the Government
now refers. OBPA required Interior to impose the contract-violating delay
and changed pre-existing contract-incorporated requirements in several
ways. By communicating its intent to follow OBPA, the Government was communicating
its intent to violate the contracts. Pp. 8-14.
(b) The Government's contract breach was substantial,
for it deprived the companies of the benefit of their bargain. Under the
contracts, the incorporated procedures and standards amounted to a gateway
to the companies' enjoyment of their rights to explore and develop oil.
Timely and fair consideration of a submitted Plan was a material condition
of the contracts, yet the Government announced an OBPA-required delay
of 13 months minimum, and the delay turned out to be at least four years.
This modification of the procedures was not technical or insubstantial,
and it amounted to a repudiation of the contracts. Pp. 15-16.
(c) Although acceptance of a once-repudiated contract
can constitute a waiver of the restitution right that repudiation would
otherwise create, none of the events that the Government points to--that
the companies submitted the Plan to Interior two days after OBPA became
law, that the companies subsequently asked the Commerce Secretary to override
North Carolina's objection to the CZMA certification, and that the companies
received suspensions of their leases pending OBPA-mandated approval delays--amounts
to significant post-repudiation performance. Pp. 16-18.
(d) Finally, the Government's argument that OBPA caused
the companies no injury because they could not have met the CZMA consistency
requirements misses the point: The companies seek not damages for breach
of contract but restitution of their initial payments. Because the Government
repudiated the contracts, the law entitles the companies to that restitution
whether the contracts would, or would not, ultimately have produced a
financial gain or led them to obtain a definite right to explore. Pp.
18-19.
177 F.3d 1331, reversed and remanded.
Breyer, J., delivered the opinion of the Court, in which
Rehnquist, C. J., and O'Connor, Scalia, Kennedy, Souter, Thomas, and Ginsburg,
JJ., joined. Stevens, J., filed a dissenting opinion.
=========================================
EOIN O'DELL <== Previous message Back to index Next message ==> |
||||||||||||
![]() |
![]() |
» » » » » |
|
![]() |
|||||||||
![]() |